2731 Lyons – Week 8 AP

Another slow week at 2731 Lyons. Progress this week was mostly on the roof. We had the missing baffles installed, finished off all the penetrations, cleaned up the eves, and added gutters on the west side. Also installed the roof over the front porch. Not much to see this week, so I didn’t take any new pictures.

By the end of this week we should have insulation and Sheetrock, so you’ll be able to get a feel for the interior spaces. Stay tuned!

2 Responses to 2731 Lyons – Week 8 AP

  1. Tammy Lopez January 10, 2013 at 7:59 pm #

    I’ve been looking at the pictures you are doing a great job I feel so good you kept a little purple in it hope to stop by soon.

  2. jrobillard January 10, 2013 at 8:26 pm #

    Glad you approve. we’ll have more purple inside. I’ll post the interior colors next week.